|
Estimating
Guide
By
RS MEANS Estimating Handbook
Types of
Estimates
Several
different levels of estimates are used to project construction costs. Each has
a different purpose. The various types may be referred to by different names
and some may not be recognized by all as necessary or definitive, though most
estimators will agree to several basic levels, each of which has its place in
the construction estimating process. In this text, the levels of estimates are
broken down as follows.
1. Order
of Magnitude Estimates: The order of magnitude estimate could be loosely
described as an educated guess It can be completed in a matter of minutes
Accuracy is plus or minus 20%. 2.
Square Foot and Cubic Foot Estimates: This type is most often
useful when only the proposed size and use of a planned building is known Very
little information is required Accuracy is plus or minus 15%. 3.
Assemblies Systems Estimate: An assemblies estimate is best used
as a budgetary tool in the planning stages of a project Accuracy is expected
at plus or minus 10%. 4.
Unit Price Estimate: Working drawings and full specifications
are required to complete a unit price estimate It is the most accurate of the
four types but is also the most time consuming Used primarily for bidding
purposes, accuracy is plus or minus 5%. Order
of Magnitude Estimates:
The Order of Magnitude estimate in be completed when only minimal information
is available. The proposed use and size of the planned structure should be
known and ay be the only requirement The "units can be very general and
need not be well defined. For example "An office building for a small
service company in a suburban industrial park will cost about $500,000"
This type of statement (or estimate) can be made after a few minutes of
thought used to draw upon experience and to make comparisons with similar
projects from the past While this rough figure might be appropriate for a
project in one region of the country, an adjustment ay be required for a
change of location and for cost changes over time (price changes, inflation,
etc). Square
Foot and Cubic Foot Estimates: The use of Square Foot and Cubic Foot estimates is most
appropriate prior to the preparation of plans or preliminary drawings, when
budgetary parameters are being analyzed and established Costs may be broken
down into different construction components, and then into the relationship of
each component, then the project as a whole, in terms of costs per square
foot. This breakdown enables the designer, planner or estimator to adjust
certain components according to the unique requirements of the proposed
project. Historical
data for square fool costs of new construction are plentiful. However, the
best source of square foot costs is the estimator's own cost records for
similar projects, adjusted to the parameters of the project in question. While
helpful for preparing preliminary budgets, Square Foot and Cubic Foot
estimates can also be useful as checks against other, more detailed estimates.
While slightly more time is required than with Order of Magnitude estimates, a
greater accuracy (plus or minus 15%) is achieved due to more specific
definition of the project. Assemblies
(or Systems) Estimates:
Ever increasing design and construction costs make budgeting and cost
efficiency increasingly important in the early stages of building projects.
Never before has the estimating process had such a crucial role in the initial
planning Unit Price estimating, because of the time and detailed information
required, is not suited as a budgetary or planning tool. A faster and more
cost effective method is needed for the planning phase of a building project,
this is the "Systems," or "Assemblies" estimate. The
Assemblies method is a logical, sequential approach which reflects how a
building is constructed. Twelve "Uniformat" divisions organize
building construction into major components that can be used in Assemblies
estimates. These Uniformat divisions are listed below:
Assemblies Estimating DivisionsDivision
01-Foundations Each
division is further broken down into individual assemblies. Each individual
assembly incorporates several different items into a system that is commonly
used in building construction. In
the Assemblies format, a construction component may appear within more than
one division For example, concrete is found in Division 1- Foundations, as
well as in Divisions 2,3 and 12 (see list above). Conversely, each division
may incorporate many different areas of construction, and the labor of
different trades.
A great advantage of the Assemblies estimate is that the
estimator/designer is able to substitute one system for another during design
development and can quickly determine the cost differential The owner can then
anticipate accurate budgetary requirements before final details and dimensions
are established. Final
design details of the building project are required for a Unit Price estimate.
The Assemblies method does not require such details, but the estimators who
use it must have a solid background knowledge of construction materials and
methods, Building Code requirements, design options, and budgetary
restrictions. The
Assemblies estimate should not be used as a substitute for the Unit Price
estimate. While the Assemblies approach can be an invaluable tool in the
planning stages of a project, it should be supported by Unit Price estimating
when greater accuracy is required. Unit Price
Estimates
The
Unit Price estimate is the most accurate and detailed of the four estimate
types and therefore takes the most time to complete. Detailed working drawings
and specifications must be available to the unit price estimator. All
decisions regarding the building's materials and methods must have been made
before this type of estimate can be completed. There are fewer variables, and
the estimate can, therefore, be more accurate. The working drawings and
specifications are needed to determine the quantities of materials, equipment,
and labor. Current and accurate costs for these items (unit prices) are also
necessary. Because
of the detail involved and the need for accuracy, Unit Price estimates require
a great deal of time and expense to complete properly. For this reason, Unit
Price estimating is often used for construction bidding. It can also be
effective for determining certain detailed costs in conceptual budgets or
during design development. Most construction specification manuals and cost
reference books, such as Means' Building Construction Cost Data, divide
all Unit Price estimating information into the sixteen CSI MASTERFORMAT
divisions. Before
Starting the Estimate In
recent years, drawings and specifications have become massive volumes
containing a wealth of information. It is of utmost importance that the
estimator read all contract documents thoroughly. They exist to protect all
parties involved in the construction process. The contract documents are
prepared so that the estimators will be bidding equally and competitively,
ensuring that all items in a project are included. The contract documents
protect the designer (the architect or engineer) by ensuring that all work is
supplied and installed as specified. The owner also benefits from thorough and
complete construction documents, being guaranteed a measure of quality control
and a complete job. Finally, the contractor benefits because the scope of work
is well defined, eliminating the gray areas of what is implied but not stated
"Extras" are more readily avoided. Change orders, if required, are
accepted with less argument if the original contract documents are complete,
well stated, and most importantly, read by all concerned parties. During
the first review of the specifications, all items to be estimated should be
identified and noted. The General Conditions, Supplemental Conditions, and
Special Conditions sections of the specifications should be examined
carefully. These sections describe the items that have a direct bearing on the
proposed project, but may not be part of the actual physical construction. An
office trailer, temporary utilities, and testing are examples of these kinds
of items.
While
analyzing the drawings and specifications, the estimator should evaluate the
different portions of the project to determine which areas warrant the most
attention For example, if a building is to have a steel framework with a glass
and aluminum frame skin, then more time should be spent estimating Division
5-Metals, and Division 8- Doors, Windows and Glass, than Division 6-Wood and
Plastics. The estimator should determine, for a given project, the relative
proportions of each component, and estimating time should be allocated
accordingly. More time and care should be given to estimating those areas,
which contribute more to the cost of the project.
Perhaps the best way for an estimator to approach a project is to begin
with a clear mind and a clear desk. Clutter and confusion can have detrimental
effects on the efficiency and accuracy of the estimate. The Quantity
Takeoff
Quantities
may be taken off by one person if the project is not too large and time
allows. For larger projects, the plans are often split into several
disciplines (or divisions) and the work assigned to two or more quantity
surveyors. In this case, a project leader is assigned to coordinate and
assemble the estimate. When
working with the plans during the quantity takeoff, consistency is the most
important consideration. If each job is approached in the same manner, a
pattern will develop, such as moving from the lower floors to the top,
clockwise or counterclockwise. The choice of method is not important, but
consistency is. The purpose of being consistent is to avoid duplications as
well as omissions and errors. Pre-printed forms provide an excellent means for
developing consistent patterns. General
Rules for the Quantity Takeoff: General rules have been established for
improving the speed, ease, and accuracy of the takeoff process. Quantity
estimators should adhere to these rules. An accurate quantity takeoff is
critical to the accuracy of a cost estimate, since no estimate will be
reliable if a mistake is made in the quantity takeoff, no matter how precise
the unit price information may be. General Rule 1When
taking off quantities, follow the guidelines provided by the person who will
be applying unit prices to the quantities (the cost estimator). The takeoff
should be clear and informative to prevent misinterpretation. Use symbols,
sketches, or footnotes to clarify ambiguities in the takeoff. The quantity
estimator should think of him or herself as an assistant to the cost
estimator. General Rule 2A
takeoff list is not just a list of materials, but a list of measurements
separated into categories to which unit prices are applied. The quantity
sheets should be relatively simple to use. The name of the building component
is written in the far left-hand column labeled Description. The number of
components called out on the plans is listed next, followed by their
dimensions (such as length, width, and depth or height. Quantities of items
that are taken off of the component are listed in the subsequent columns. When
taking off strip footings, for example, the associated items include
structural excavation, concrete, formwork, backfill, and disposal Appropriate
units of measure, such as cubic yards of concrete, square feet of forms, and
linear feet of pour strips, are applied to each item. If
more than one building component is listed on the same quantity sheet, or if
there are several different sizes of the same component, then quantities are
listed in the appropriate columns and totaled at the bottom of the page In
this way the quantity estimator can calculate, for instance, the total number
of cubic yards of concrete needed for strip footings for the entire building
and write it in one sum at the bottom of the column labeled Concrete". General Rule 3A
quantity estimator may begin the takeoff with any building component and
proceed in the order of his or her choice. A good approach is to follow
roughly the order of the actual field construction, such as from the footings
upward to the roof This provides the quantity estimator with the clearest
mental picture of the project. If a project consists of more than one
building, each structure should be taken off separately, since unit costs may
vary from structure to structure. General Rule 4Check
the drawings and details carefully for notes such as 'NTS" (Not To
Scale), changes in the scale as it is used throughout the drawings, drawings
reduced to one-half or one-quarter their original size, or discrepancies in
the specifications and the plans. Be consistent when listing dimensions. General Rule 5Where
possible, use the dimensions stated in the drawings instead of measuring by
scale, but make a habit of frequently checking printed dimensions with a scale
or with mental arithmetic to spot draftsman's errors. Always express
dimensions in the same order, such as Length x width x height (or depth) General Rule 6Use
a systematic procedure when working with the drawings For instance, take
measurements in a clockwise direction around a floor or roof plan, first
recording the measurements of items displayed horizontally on the drawings,
and then recording those shown vertically. This method is most useful when
taking off two-dimensional areas. General Rule 7Whenever
possible, the items in a quantity takeoff should be identified by their
location on the drawings. General Rule 8A
quantity estimate is not intended for direct purchasing of materials. In fact,
many items on a quantity estimate have no material value. These are called
work items and are simply areas that require labor, such as fine grading
gravel or finishing concrete surfaces. Work items may not appear on the
drawings but are nonetheless required to complete the job. The quantity
estimator should pay close attention to areas that may contain labor
requirements. Items that do have material value are called material items.
Both material items and work items are assembled on the same form for eventual
pricing out, or cost estimating. Any item that has a cost value should be
assigned a unit of measure, even if it is only in lump sum (LS) form The term
'lump sum" is used for certain work items that cannot be measured or
expressed in any other way "LS" calls the estimator's attention to
an item that requires a judged cost allowance. General Rule 9Decimals
are used in quantity takeoff instead of fractions because they are faster,
more precise, and easy to use on a calculator. Drawing dimensions that are
given in feet and inches are converted to decimal feet, that is, feet and
tenths of a foot. General Rule 10Quantity
takeoff is performed for cost estimating purposes. Since estimating is not an
exact science, the lists of quantities need not be overly precise. An example
of unnecessary precision is calculating excavation quantities to 1/ 8".
However, a reasonable degree of precision is expected. No detailed estimator
wants to be accused of ballpark estimating. In most cases, the use of two
decimal places is sufficient for quantity surveying purposes (12' 4-1 2"
= 12.38') and easy to enter into a calculator. However, when writing the
product of the calculation, decimals are usually meaningless. Develop rules
for precision that are consistent with measurement capabilities. Below is an
example:
The quantity estimator must also learn the standards of each industry.
For instance, a lumber dimension of 12' 1-1/2" must be rounded up to14'
due to standard sawmill cutting practices. Finally,
do not convert units until all items in a column are totaled. For instance,
keep concrete in cubic feet (C F) until all of the quantities listed in the
concrete column have been added together. Then convert to cubic yards (CY) General Rule 11The
quantity estimator should add an allowance for waste to certain quantities.
Before the waste allowance is made, the quantities are referred to as net
quantities. After the allowance for waste is added, the quantities are
considered gross quantities. General Rule 12Ideally,
a second quantity takeoff should be performed by a separate individual or team
to ensure that no items have been omitted or duplicated. Unfortunately, the
personnel to perform a second estimate are usually not available, or the cost
to hire additional help is prohibitive. Typically, the quantity estimator
systematically must check his or her own work. In fact, the quantity estimator
should check the dimensions taken from drawings while someone other than the
original quantity estimator should check the extensions. General Rule 13One
way to avoid omissions and duplications is to mark the drawings as items are
taken off. Make colored pencil shadings and check marks directly on the
drawings as items are taken off. Most quantity estimators have their own
methods of marking drawings. Usually a combination of methods is used, rather
than a single method, as one kind of mark may be effective in taking off one
particular category, and different marks effective for other categories. The
quantity estimator may assume that any item on a drawing that has not been
marked has not been taken off yet. When
work is interrupted, for whatever reason, select a natural stopping point and
mark it clearly so that when work resumes, no items are missed or duplicated. Systematic
application of these rules will make the quantity estimators job faster,
easier, and more accurate Refer to the general rules in this chapter whenever
necessary. Pricing the
Estimate
When
the quantities have been determined, then prices, or unit costs, must be
applied in order to determine the total costs. Depending upon the chosen
estimating method (and thus the degree of accuracy required) and the level of
detail, these unit costs may be direct or bare costs, or may include overhead,
profit or contingencies. In Unit Price estimating, the unit costs most
commonly used are bare, or unburdened. Items such as overhead and profit are
usually added to the total direct costs on the bottom line, at the time of the
estimate summary. No
matter which source of cost information is used, the system and sequence of
pricing should be the same as those used for the quantity takeoff. This
consistent approach should continue through both accounting and cost control
during construction of the project. Types
of Costs:
Unit price estimates for building construction may be organized according to
the 16 divisions of the CSI MASTERFORMAT. Within each division, the components
or individual construction items are identified, listed, and priced. This kind
of definition and detail is necessary to complete an accurate estimate. In
addition, each "item" can be broken down further into material,
labor, and equipment components. All
costs included in a Unit Price estimate can be divided into two types direct
and indirect. Direct costs are those directly linked to the physical
construction of a project, those costs without which the project could not be
completed. The material, labor, and equipment costs mentioned above, as well
as subcontract costs, are all direct costs. These may also be referred to as
bare, or 'unburdened' costs. Indirect
costs are usually added to the estimate at the summary stage and are most
often calculated as a percentage of the direct costs They include such items
as sales tax on materials, overhead, profit and contingencies, etc. It is the
indirect costs that generally account for the greatest variation in
estimating.
Types of Costs in a Construction Estimate
The
Paperwork:
At the pricing stage of the estimate, there is typically a large amount of
paperwork that must be assembled, analyzed, and tabulated. Generally, the
information contained in this paperwork is covered by the following major
categories:
A
system is needed to efficiently handle this mass of paperwork and to ensure
that everything will get transferred (and only once) from the quantity takeoff
to the Cost Analysis sheets. Some general rules for this procedure are:
All
subcontract costs should be properly noted and listed separately. These costs
contain the subcontractor's markups, and will be treated differently from
other direct costs when the estimator calculates the general contractor's
overhead, profit, and contingency allowance. The
Estimate Summary:
When the pricing of all direct costs is complete, the estimator has two
choices: all further price changes and adjustments can be made on the Cost
Analysis or Consolidated Estimate sheets, or total costs for each subdivision
can be transferred to an Estimate Summary sheet so that all further price
changes, until bid time, will be done on one sheet. Unless
the estimate has a limited number of items, it is recommended that costs be
transferred to an Estimate Summary sheet. This step should be double-checked,
since an error of transposition may easily occur. Pre-printed forms can be
useful, though a plain columnar form may suffice. If a company has certain standard listings that are used repeatedly, it would save valuable time to have a custom Estimate Summary sheet printed with the items that need to be listed Appropriate column headings or categories for any estimate summary form are:
As items are listed in the proper columns, each category is added, and
appropriate markups applied to the total dollar values Generally, the sum of
each column has different percentages added near the end of the estimate for
indirect costs.
Since
over 50% of the work on a typical building is performed by subcontractors, two
aspects of bid preparation deserve special attention. The first is a clear
understanding of the contractor's scope of work, which is essential, not only
to compare the bids of competing subs, but to ensure that you have
included all the items that the subcontractors may have excluded (such as
cutting and patching, temporary protection, scaffolding, hoisting, etc). The
second is that subcontractor prices typically do not arrive until bid day,
which leaves little time to analyze competing bids, and makes last-minute gaps
in coverage difficult to address if you have not done the necessary
coordination with these subs beforehand.
|
|
Send mail to webmaster@peoplelogicsoftware.com with
questions or comments about this web site. |